13:00
15:00
2.00
Break out logging tools from reamer and l/d logging tools. Catch ball on logging tool is 2 3/8".
15:00 15:00 0.00
Break down Thrubit Bit BHA and L/D.
15:00 15:30 0.50
P/U two jts. Of D/P & M/U 7 7/8" insert bit, bit sub w/float for clean out run.
15:30
15:45 0.25 Install rotating head.
15:45
21:00 5.25 TIH to 13545'.
21:00
21:15
0.25
Kelly up and wash 25' to bottom no
fill.
21:15
22:30
1.25 Circulate hole.
22:30
22:45
0.25 R/U Fluid Caliper
22:45
1:00
2.25
Circulate fluid caliper around. Annular cuft @ 2677
1:00 1:15 0.25 R/U Bull Rogers L/D machine.
1:15
1:30
0.25
R/D Fluid Calpier.
1:30
1:45
0.25
Set kelly back and install elevators.
1:45 2:00 0.25 Safety meeting and adjust breaks.
2:00 6:00 4.00
L/D 4 1/2" DP.
Logging tool was stuck in our reamer, 2 3/8 catch ball would not pass
thru,
we were able to recover a
DSN-GR log on the entire well during POH.
Diesel used 874 gals. Diesel on hand 6582 gals.
01/08/2013
6:00 9:30 3.50
L/D 4 1/2" DP.
9:30 10:15 0.75 Kelly up and break down kelly.
10:15
12:15
2.00
Continue to L/D 4 1/2" DP.
12:15 13:15 1.00
Pull wear bushing and held PJSM with Bull Rogers casing crew & R/U casers.
13:15 0:00 10.75
M/U 5 1/2" shoe track and TIH with 5 1/2" 23# L-80 LT&C casing. Filling every 30 jts. Run a total of 322 jts.
0:00 0:00 0.00
Land casing @ 13,567'. Casing went to bottom with no problems.
0:00 0:45 0.75
. . j
R/D casers and L/D machine.
0:45 2:15 1.50 Circulate 5 1/2" casing with full returns.
2:15 6:00 3.75 Held PJSM with schlumberger cementers and R/U cementers. Test lines to 4000 psi. pumped 10 bbls. Water
6:00 6:00
0.00
spacer, 25 bbls. Mudpushll followed by 385 sxs. Of class H blended w/42 pps Litepoz 3 extender lead
6:00 6:00
0.00
@ 11.8 ppg, yield of
2.61
& 14.98 watergal/sk. Followed by 990 sks of TXI Liteweight tail cement @ 13.0 ppg
6:00
6:00
0.00
yield of 1.42 and 7.29 watergal/sk. Shut down and wash up lines. Drop plug and displace with 286.6 bbls. Of
6:00 6:00 0.00 fresh water. Land plug @1700 psi and bump plug to 2200 psi. 500 psi over. Held pressure for 5 mins. And
6:00 6:00 0.00 Released pressure and checked floats, floats
held.
R/D cementers. Got back 2 bbls. .Of water after
6:00 6:00
0.00
releasing pressure. Had full returns thru out the
job.
Plud down @ 05:30 am on 1/8/2013.
Informed Jack Johnson w/BLM on
1/7/2013
@ 08:00 am on casing and cement job.
Diesel used 552 gals. Diesel on hand 6030 gals.
19 |